The Grid Code Specifications for Demand Connections define the technical conditions that must be met for electrical equipment to be connected to the Finnish power grid. Fingrid sets these requirements based on the European Network Codes to ensure grid reliability, security, and equal operating conditions. In data center projects, compliance with the Grid Code is a critical part of the grid connection process.
The current Grid Code 2018 requirements apply to all projects where binding equipment contracts have been signed after 7 September 2018. They specify in detail what must be submitted and how compliance is demonstrated. We ensure that design, testing, and documentation meet these requirements, enabling a smooth and approved grid connection process.
Upcoming Changes (Grid Code 2026)
Fingrid is updating the technical requirements for demand connections, with the new Grid Code 2026 to be published for comments during 2025. The update aims to further harmonize and clarify connection conditions. We closely monitor these developments and ensure that upcoming requirements are taken into account early in the client’s project.
The Grid Code process requires submitting comprehensive connection data to Fingrid, including information on 110 kV substations, transmission lines, transformers, compensation equipment, and operational characteristics. Fingrid may also require simulation models for plants with large converters or arc furnaces. We prepare the necessary calculations, models, and documentation to ensure full compliance.
Demonstrating compliance involves equipment testing and simulation. This includes protection and relay testing, disturbance simulations, and frequency and voltage response tests. When required, advanced simulations using PSCAD or PSS/E are performed. We plan and coordinate the testing process and ensure that all results are properly documented and reported.
By outsourcing the Grid Code process, clients gain certainty that all requirements are met correctly and on schedule. We are familiar with Fingrid’s procedures and regulatory updates from Grid Code 2018 to the upcoming Grid Code 2026, combining technical expertise with strong project management to minimize the risk of delays or rejections in the grid connection process.
Free webinars
Data Center Projects – Webinar Recording
Data centers are a critical part of modern digital infrastructure, and their construction requires thorough preparation and close collaboration between multiple stakeholders. This recording walks through the key factors that determine the success of data center projects, from design to implementation.
The webinar explores how financial foundations, location, and risk analyses affect project success, and why clear communication between the client, designers, contractors, and consultants is essential. Through practical examples, it illustrates what effective project communication looks like and how schedules and risks can be identified and managed from the early stages. It also examines how to ensure the right expertise and sufficient resources throughout the entire project lifecycle.
The recording provides practical insights and tools to help ensure a smooth and successful execution of your next data center project.
Subscribe to receive the webinar to your email
By downloading the webinar recording, you agree to subscribe to Despro’s newsletter. Through it, you’ll receive current insights, expert content, and news from the energy and telecommunications sectors. You can unsubscribe at any time via the link included in the emails.
contact us
How can I help you?
Karoliina Tuominen has a long background and experience in the industry. She can create a customized service according to the needs.